(6)
appears feasible to complete the arch in three more seasons to a junction with
first-order triangulation in the east on the north shore of the Gulf of St. Lawrence.
The shoran trilatération is of necessity the first step, and auxiliary stations will
have to be established in any area concurrent with its use for shoran-controlled
photography. The lines in general are too long for signal reception unless working
within 150 miles of each antenna, and in many areas they are not properly placed
to secure favourable intersection of position.
Since in geodetic surveying and mapping it is the sea-level distance between
stations which is required, it is necessary to consider trilatération sufficiently
strong in a geometrical sense to give not only length to a certain accuracy but at
the same time to give position to a relatively high degree of accuracy. Triangula
tion requires the measurement of angles and for a quadrilateral in which all angles
are measured, four geometrical conditions must be satisfied. In trilatération the
measurement of the six lines of a quad, imposes only one condition and hence
there is a falling-off in strength inherent in the method. To offset this, stations
should be arranged in pentagon pattern so that extra lines of measurable length
may be introduced from stations in one figure to stations in adjacent figures thus
giving overlap. We have endeavoured to work to a standard of two lines more per
station than that required to fix the stations. In practice there are limitations in
regard to the maximum operating altitude of the line-crossing plane and to the
distance at which the signals, due to lack of strength, may be received from the
ground stations. These limits are with our present equipment 20,000 feet in
altitude and some 165 miles in length. Thus the maximum length of measurement
is approximately 330 miles.
Line Crossing anti Length Measurement
The shoran instrument in the plane flying at uniform ground speed, height
and direction, in the vicinity of the centre of the line, emits group pulses (20 per
second) which are alternately sent to the terminal ground stations on frequencies
of 230 and 250 mgc. and are then delayed a fixed amount and returned on a
common frequency of 300 mgc. The elapsed time between dispatch and reception
is available on mileage dials, which together with other dials, are photographed
at intervals of three seconds. It is evident that the true sum of the distances,
plane to stations, is greater on each side of the actual crossing and is a minimum
at the crossing. If time is plotted against sum the plot approximates a parabola
and a mathematical curve of best fit will determine the minimum sum distance
corresponding to each line-crossing flight.
All lines of the project have been measured to a minimum standard of sixteen
line-crossings, of which two groups of eight each were done on different days to
ensure a change of atmospheric and other conditions and to reveal unstable
equipment.
As an example let us now consider the results obtained for the line Fort
Simpson—Peace, Tables I-II, which is the greatest length so far measured in our
operation.