TABLE 1 :
LANDSAT - 4 PROGRAM FEATURES
• SIGNIFICANT INCREASE IN DATA RATES (TM) AND VOLUME OVER
EARLIER LANDSATS
• 48-HOUR IMAGE PROCESSING TURNAROUND TIME
• SUB-PIXEL GEOMETRIC ACCURACIES:
- TEMPORAL REGISTRATION = 0.3 PIXELS
- GEODETIC RECTIFICATION = 0.5 PIXELS
• MULTIPLE COMMUNICATION PATHS FOR TELEMETRY, COMMAND
AND IMAGERY
- TRACKING AND DATA RELAY SATELLITE SYSTEM (TDRSS)
- GODDARD SPACE TRACKING AND DATA NETWORK (GSTDN)
- TRANSPORTABLE GROUND STATION (TGS)
- FOREIGN GROUND STATIONS
• NEW MULTI-MISSION MODULAR SPACECRAFT USED
- PLATFORM IS 10 TIMES MORE STABLE THAN EARLIER LANDSATS
- GLOBAL POSITIONING SYSTEM EXPERIMENT PROVIDES
IMPROVED EPHEMERIS DATA FOR GEODETIC ACCURACIES
- SHUTTLE COMPATIBLE FOR RETRIEVAL
• NASA TURNOVER TO NOAA IS TO OCCUR IN STAGES: MSS FIRST, THEN TM
• "LESSONS LEARNED" DURING LANDSAT 2 AND 3 PROCESSING WERE IMPLEMENTED AS
PART OF LANDSAT-4 GROUND SEGMENT
- DEVELOPED WITH OPERATIONAL PHILOSOPHY
- ABILITY TO FULLY EVALUATE OUTPUT PRODUCTS INTERNALLY
- BUILT IN PARAMETER CHECKS AND CHECK POINTS THROUGH-OUT THE
PROCESSING CYCLE
- SINGLE PRIME CONTRACTOR FOR OVERALL DESIGN, DEVELOPMENT, INTEGRATION,
TEST AND OPERATION
• MSS INTERFACES WITH EROS DATA CENTER ARE ESSENTIALLY UNCHANGED