€—
res
pre re orne oran
—
IIS IMAGES
The work of marking the more than 200 points,
among which the data points to be used for
orientation and those to be measured, was very
expensive. 3 people were needed for 4 days and a
crane for access to the structure's higher areas.
The onshore data point's coordinates were
determined using the topographic technique of
forward intersection carried out using a WILD
T2000 theodolite.
3 sets of measurements were made, each with double
straight/reverse readings. The points on the
Structure were defined during the loading phase.
In this case an operator collimated the 3 points
with a prism using a diastimeter in the few
seconds that the structure was stationary.
A single reference system was used for all the
data points' coordinates defined topographically.
This system will then be used also for
measurements carried out at the stereoplotter.
Precision reached in defining the data points was
t 1 mm.
4.3 Photogrammetr
The survey to give an undeformed reference
geometry was carried out from bases 1 and 2
(figure 1), shooting respectively the structure's
bottom and top.
The bases were distributed following an alignment
parallel to row 2 of the jacket and 50 meters
away. One metric camera placed at each of the
four positions was used.
8 photograms were taken with a vertical
inclination of +15°.
The survey of the loading was carried out from a
double base with 3 cameras. In fact it was
necessary to sufficiently cover the jacket's
surface with the photograms. And, if this was
easy to achieve onshore it was not easy for the
part in the boat. The problem was overcome by
horizzontally inclining the cameras.
Three cameras were used, two were connected to
each other and a third was independent but
synchronised manually.
Loading operations were carried out from 5.00pm to
midnight on 10/5/90. The most important phases of
the operation therefore took place at night and
very long exposition times were needed.
Compatibly with the loading movements, exposition
times of 15-20 seconds during some of the extended
stops. 27 shots were taken using a KODAK PAN 200
film with a 24 DIN sensitivity. Every camera had
a container for roll-films equipped with an
aspirator to keep the film flat at the moment of
shooting.
5. MEASUREMENT OPERATIONS
5.1 Photogram orientation
The topographic calculations were made using a PC
Olivetti M24 with dedicated software.
Plotting was made using a WILD AC1 analytical
plotter conected to a Nova 4X Data General, with a
PMO package programs.
The photograms were selected on the basis of
qualitative criteria and in such a way as to have
a detailed description of the loading phases.
Despite the availability of three photograms for
each phase, having used 3 metric cameras to shoot
the loading phase, only the photograms of the two
A and AR cameras of base 4 (sea-side) were used.
In fact, the third photogram did not offer great
improvements for the number of points and the
precision of the measurements. This photogram was
used only in one case where the orientation of a
sea side couple was difficult.
5.2 Plotting
14 pairs of photograms were plotted giving a good
description of the structure's deformative
phenomenon.
The point which can be collimated by the operator
were measured for each stereoscopic model.
Contrary to expectations, the measuring
procedure’s limits were not the lack of visibility
of the points due to lack of light or great
distance. The biggest problem was the blocked
view because of different types of obstacles. In
fact, to be used, each point had to be seen on 4
photograms, two for the reference pair and two for
the comparison pair.
On the other hand it was decided not to measure
the points without a target to avoid reducing the
precision.
The quality of the measurements obtained by the
plotting may be estimated approximately on the
basis of the measurements at the data points
defined topographically.
These data were included on the plot protocols.
The average of the standard deviation on the data
point readings was the following:
reference pairs
Py = 0.0014 mm
Dn = 1.43 mm Dh = 1.69 mm
pairs during loading
Py = 0.0023 mm
Dn = 2.21 mm Dh = 2.83 mm
where Py is the residual parallax value, Dn is the
accuracy in the plane normal to the optical axis
and Dh is the accuracy of the coordinates in the
direction parallel to the optical axis.
6. DATA PROCESSING
The data obtained by the plotting measurements
were recorded according to the string type:
ID, X, Y, Z
where ID is the identifier for each point, and X,
Y and Z are the coordinates according to the
absolute reference system. A file was created for
every position of the platform during the
load-out.
These data were then transferred to a personal
computer where the subsequent processing was
carried out.
In the first phase the points were ordered
according to the identifier's progressive order.
Then every data file for each loading phase was
compared with the file obtained during the
reference phase following this process:
ID, X(0), Y(0), Z(0) reference phase file
ID, X(i), Y(i), Z(i) loading phase file
DX(i) » X(i) - X(0)
DY(i) s Y(i) - Y(O)
DZ(i) = Z(i) - Z(0)
In order to simplify the interpretations, only the
DZ(i) vertical displacement were considered in the
following steps.
Table 1 shows the results obtained by this
operation. Each column represents the movements
of all the points for each phase. The points
which were not measured in any of the loading
phases or in the reference situation were