lly
ed,
of
are
on-
ion-
nge
180-
ical
| for
)se-
ich,
MONITORING ONE OF EUROPE’S LARGEST RETAINING WALLS USING OBLIQUE AERIAL
PHOTOGRAPHY
D M Stirling, J H Chandler & J S Clark
Engineering Surveying Research Centre, Department of Civil Engineering
City University, London, United Kingdom
ISPRS Commission V
ABSTRACT:
Oblique aerial photography acquired with a hand held Zeiss 300 mm UMK camera from a helicopter is being used for the
long term monitoring of two large retaining walls currently under construction. The location of the site has dictated the
use of a helicopter to obtain suitable convergent geometry so that high homogeneous precision can be obtained. Various
cameras and emulsions have been tested in order to develop a system to satisfy the unique problems of the task. Preliminary
results (using inner- constraint bundle methods and congruency tests), including detected movements and rotations of
individual pre-cast concrete panels which comprise the walls are discussed. Methods for visualising the displacements
and rotations are also considered.
KEY WORDS: Deformation, Engineering, Hand held, Helicopter, Monitoring, Oblique, Presentation
1. INTRODUCTION
The ASS is a major trunk route in North Wales to the port
of Holyhead on the island of Anglesey. Over the last
twenty years most of the route has been converted to dual
carriageway. One of the few remaining single
carriageway sections is the short stretch between
Penmaenmawr and Llanfairfechan. Work has now begun
on providing a second carriageway at this point. This
involves driving a 880 metre long tunnel through a granite
headland. At each portal large retaining walls are being
constructed. The wall at the west portal will be 220 metres
long and 35 metres high thus making it one of the largest
retaining walls in Europe when completed. These walls
are being constructed from the top down and consist of 3
metre by 2 metre pre-cast concrete panels anchored to the
rock with two tensioned rock anchors per panel.
The Ground Engineering Division of the Transport and
Road Research Laboratory (TRRL) of the Department of
Transport are undertaking a monitoring study of the
behaviour of these retaining walls during construction and
after completion. One of the aspects of this exercise is
deformation monitoring. Based on previous monitoring
work (Cooper and Clark, 1984) TRRL approached City
University for advice on how monitoring of deformation
of these structures could be achieved.
2. PRELIMINARY WORK
The situation of the site concerned indicated that
photogrammetry provided the best and most efficient
method of monitoring the walls. The site is on the side of
a cliff above the sea with the existing road being 28 metres
above a railway at the shoreline. Monitoring by
traditional geodetic surveying methods would not yield
sufficiently accurate and homogeneous results because of
poor network geometry, as all sight lines would have to
be observed up from the existing road level and would
result in highly inclined lines of sight to points on the top
half of the walls. For good redundancy an excessive
number of instrument stations would be required.
Additionally as monitoring was required during
construction it would be almost impossible to sight to
targets through all the construction plant and other
obstructions that would be on site, particularly in the early
stages of construction. Using photogrammetry it would
be possible to get much better convergent geometry by
using camera stations raised above the existing road level
and most of the plant. One possibility investigated was to
employ an elevating platform to raise the camera to the
high positions. However this would have resulted in
severe congestion to the existing road, which is a major
trunk route, with the platform parked at the roadside with
outriggers extended, especially during the construction
phase.
Low altitude vertical aerial photography has been used in
the past for monitoring unstable hillsides (Fraser, 1983,
Fraser and Gruendig, 1984). In this present study oblique
aerial photography of the almost vertical walls seemed
ideal and therefore it was decided to use a helicopter to
obtain the required photography. This had the added
advantage of rapid acquisition of all the required
exposures per site. Helicopters with special mounts have
been used to acquire vertical photography (Stanbridge,
1987) but in this instance it was very quickly decided that
the camera would be hand held for the oblique
photography. Therefore with no requirement for
specialised camera mounts not only could the cost be
reduced but, more importantly, allowed much greater
flexibility in chartering the most conveniently situated
helicopter.
In order to obtain a large enough image scale for accurate
measurement it was decided to use a Zeiss Jena UMK
30/1318 camera with 300 mm lens and glass plates.
Consideration was given to using a film back but this
would have proved too heavy to hold conveniently and the
weight of the control box and provision of a power supply
was also a problem. It was felt that with some practice
glass plates could be changed quickly enough for the
operation to run efficiently.
It was also decided to hire a Linhof Aerotechnica 45 EL
camera with a 250 mm lens for the first sortie to compare
the operation of the two cameras in the helicopter and also
their suitability for providing accurate results.
One of the major tasks was the design of a suitable hand
held mount for the UMK. The resultant design had to be
strong enough to support the weight of the camera but
enable pointing and plate-changing to be accomplished
easily and quickly. The final design (Figures 1 and 2)
utilised the hamess of a bus conductor's ticket machine
attached to a metal plate from which a short aluminium