The International Archives of the Photogrammetry, Remote Sensing and Spatial Information Sciences. Vol. XXXVII. Part B5. Beijing 2008
996
The speed of data acquisition by terrestrial laser scanning with
the mobile mapping system of VISIMIND could be increased
significantly. 33 blocks could be scanned in 33 working days
until the end of August 2007. Usually, scanning could be
carried out five days per week (Mo-Fr, plus Sunday) starting at
6.30 am until 2 pm of each working day. Consequently, the
laser scanning of the remaining 50 blocks could be finished
with the mobile system by November, 8 lh , 2007 with the
improved total production rate of ~600m per hour, while post
processing of the multiple sensor data took until January 2008.
The production rate was mainly 1:10, i.e. for one hour scanning
10 hours post processing was needed. In total, 12 operators of
the laser scanning group were supporting the data post
processing of the mobile mapping system during the major
processing phase. Nevertheless, approximately 2% of the area
(30ha) could not be scanned by mobile terrestrial laser scanning
(TLS) due to traffic restrictions and environmental conditions.
This remaining 2% of the total area must be scanned by static
TLS at the end of the project in order to complete the data
acquisition. At least two months will be needed for scanning by
static TLS using all available laser scanning systems.
4.3 Digital photogrammetry
For photogrammetric documentation of the building facades as
mentioned before, pre-calibrated SLR cameras Nikon D70 with
14mm and 28mm lenses were used. The acquired images were
processed in combination with the static terrestrial laser
scanning data. When the mobile system was used for data
acquisition, only the images of the integrated oblique and
horizontal cameras (Figure 8) were used for mapping. The
upper sideward looking camera is vertically rotated against the
lower camera by approximately 34°, enlarging the vertical field
of view of the camera system to approximately 86°, so that the
camera system starts at an angle looking down to the street.
Figure 8. Oblique and horizontal camera integration in the
mobile system (left), image taken by oblique camera (right)
5. MAPPING OF FACADES
The geo-referenced point clouds from the laser scanning group
were used for line mapping of the facades in a plot scale 1:200.
The point clouds were segmented by two people using Cyclone
software before mapping (Figure 9) to eliminate unnecessary
points and to reduce the data volume to the requested minimal
portions for the mapping software.
In this project generation of façade maps with 1:200 plot scale
is required. This extreme demand corresponds to a standard
deviation of the positions with 0.2mm in the map and 4cm in
the object space, but this extreme accuracy is required only as
relative accuracy; for the absolute accuracy a standard deviation
of 0.5mm in the map, corresponding to 10cm in object space
should be sufficient. As a tolerance limit three times the
standard deviation has been accepted. Therefore, the control
point configuration and accuracy must always be checked to
obtain this accuracy. While all problems of static and mobile
scanning were solved, the delay in the control point
determination was a bottleneck in the production.
Figure 9. Segmentation of a point cloud
The facade mapping group consists of 34 operators using 34
licences of the Menci-software Z-MAP Laser from Italy, which
is able to process laser scan data and rectified photogrammetric
images simultaneously for line mapping with limited AutoCAD
functionality. It was estimated that approximately 5 million m 2
of facades have to be mapped. The production rate was similar
to the static laser scanning group: 80 ha with 32 operators in
approximately 6 months. With regards the facade area, in total
81,000 m 2 could be finished in 39 days, which corresponds to
65 m 2 per person per day. The production rate could be
increased from 60 m : of facade/day/operator (March 2007) on
average to 140 m 2 /day (October 2007), which is more than a
factor of a 2 time increase. If one assumes in total 5 million m 2
façade area for mapping of the Historic Peninsula, it
corresponds to an estimated mapping time of approximately
five years with 34 operators working on 210 days per year. This
estimation indicated that the mapping could not be finished
before the deadline of the project.
For data processing in Z-MAP all related data of the segmented
part (point cloud, Nikon image(s), camera calibration file) was
saved in one directory using the name of the block plus a suffix,
e.g. 900 01. This block name is defined in the cadastre map.
The HP workstations xw8200 used are equipped with dual
XEON Processors (3.6 GHZ), 4 GB RAM and nvidea Graphic
Cards with 256 MB RAM. For facade mapping the point cloud
and one oriented image of the façade were used. Thus, the
orientation of the photogrammetric image (usually recorded
with the 14 mm lens) had to be determined by resection in
space using at least five well distributed corresponding points
(usually comers of windows) in the point cloud and in the
image. For the adjustment of the spatial resection the calibration
data of the pre-calibrated NIKON D70s are used. Usually the
residuals of the control points were in the range of some
millimetres, which indicated that sufficient results have been
achieved. To carry out mapping with Z-MAP the images had to