T2D0o4-'v L.774LlL1o0 Lc navirrldiud iwil—-ULtLter aircrart. 
  
Desert Pumping Project. Meetings on using the APTS to profile the Great 
salt Lake Desert began in January 1985, and an agreement for the project 
was signed on April 15, 1985. 
DESIGN OF THE PROFILING SURVEY 
The transition from the APTS application testing program to the Salt Lake 
Desert Profiling Project was significant and offered a considerable chal- 
lenge. Several factors about the new project are important: 
e The size of the project, 40 x 40 miles, was much larger than any 
previous project. Whereas the previous projects required only a 
few hours of flying to obtain the profile data, the Salt Lake 
Desert Profiling Project would require 30-50 hours of flying. 
® All the previous surveys were in eastern Massachusetts with cool 
temperatures, elevations near sea level, moderate topographic 
relief, many lakes and rivers, and thick stands of timber. With 
respect to all of these environmental factors, the Salt Lake 
Desert Project presented extremely contrasting conditions. 
The selection of retroreflector sites was influenced by the location of 
existing elevation control. Fortunately, control elevations of sufficient 
accuracy were available at many points within the project area. Most were 
the result of USGS map control surveys made in 1973 when elevations were 
established at many of the township corners. Elevations also were 
recently established in the remote regions of the desert by Caldwell, 
Richards, and Sorensen Engineers under contract to the Utah Department of 
Natural Resources. This fortunate coincidence of the desired retro- 
reflector spacing matching the distance between township corners (6 miles 
or about 3 minutes of flying time) was utilized, and the retroreflectors 
were generally positioned at township corners (fig. 2). Profile flight- 
lines were planned in a crisscrossing pattern such that profiles were 
obtained between all adjacent retroreflectors. This profile pattern 
agreed well with an earlier estimate that profiles not be separated by 
more than 2 miles in order to capture sufficient topographic detail in the 
mud-flat type desert country. 
The project was divided into seven flight mission areas (fig. 3). Small 
areas were necessary because of the limited number of retroreflectors 
available (28) and because the aircraft flight time is limited to about 
2 1/2 hours due to the amount of fuel that can be carried. The two flight 
missions for area C are given in figures 4 and 5. The first flight pro- 
duced the diagonal profiles and the second produced the profiles in the 
cardinal directions. Both areas B and C were covered by the flightline 
shown in figure 5. 
RETROREFLECTOR SITE SURVEYS 
The ground survey work began in late May 1985 with a USGS field party 
operating from Wendover, Utah. A Bell Ranger helicopter was made avail- 
able to provide transportation into the remote regions of the project. At 
that time of year, most of the Great Salt Lake Desert is inaccessible by 
ground travel due to excessive moisture, which forms a thin surface layer 
of slick mud. 
277 
 
	        
Waiting...

Note to user

Dear user,

In response to current developments in the web technology used by the Goobi viewer, the software no longer supports your browser.

Please use one of the following browsers to display this page correctly.

Thank you.