cal
on,
ion
ne,
ind
ind
the
ind
cle
0st
eir
m°,
vith
tive
g a
the
ally
the
on a
erial
e 10
udy,
se it
y to
lates
nizes
International Archives of the Photogrammetry, Remote Sensing
earthwork costs using linear programming (LP), and estimates
sediment production. The economic distribution of cut and fill
quantities is determined by implementing the LP method of
Mayer and Stark (1981). This method represents the earthwork
allocation better than the other methods due to considering
possible borrow and landfill locations and various soil
characteristics along the roadway. Besides, it provides the
optimal solution to the earthwork allocation problem. A linear
programming code, using the idea of simplex algorithm
(Bowman and Fetter, 1967), is developed to incorporate this
method into the model.
The average annual volume of sediment delivered to a stream
from the road segments is estimated by using the method of the
Geographic Information Systems (GIS) based erosion delivery
model, SEDMODL (Boise Cascade Corporation, 1999). Some
of the road erosion factors considered in this model include
geologic erosion rate, road surface type, traffic density, road
width and length, average road slope, average precipitation
factor, distance between road and stream, cut slope cover
density, and cut slope height. SEDMODL reasonably predicts
the sediment delivery and defines the road segments with high
sediment production.
To develop additional road alignment alternatives, various
feasible road paths can be traced out by the designer. For each
alternative, the model follows the same procedure to find the
optimal vertical alignment with minimum total cost. Therefore,
the designer can quickly generate many alignments and select
the optimal one among the alternatives in an efficient way.
3. RESULTS AND DISCUSSION
The model was applied to a study area of 55 hectares, located in
the Capitol State Forest, Washington, the USA. The high-
resolution DEM (Imx1m) of the study area was obtained from
LIDAR (Aerotec, 1999). The attribute data including soil,
hydrology, and geology data were provided by Washington
Department of Natural Resources. Road design specifications
(Table 1) and cost data in US dollars (Table 2) were obtained
from the local sources in Pacific North West (PNW) (Kramer,
200; USDA Forest Service. 1999).
Initial road path was generated by establishing six intersection
points on the 3D image of the terrain based on DEM data from
LIDAR, while considering road design specifications and
environmental requirements (Figure 2). The unit cost of this
initial path was $36.88/m. Then, using optimization techniques,
Table 1. The road specifications used in the example
and Spatial Information Sciences, Vol XXXV, Part B7. Istanbul 2004
Table 2. Local unit cost data for road construction in PNW
Cost Items Costs
Construction staking $ 778/km
Clearing and grubbing $3700/ha
Earthwork
Excavation $1.6/m°
Haul $1.3/m^-km
Embankment $0.6/m°
Disposal $0.1/m*
Borrow material
Excavation $1.8/m°
Haul $1.3/m’-km
Embankment $0.6/m°
Surfacing
Base course $3.9/m°
Traction surface $11.8/m°
Drainage and riprap
Culvert $25 meter
Riprap $10/m°
Watering $3/kilo liter
Seeding and mulching
Material $0.5/kg
Application $550 /ha
the model located the optimal vertical alignment with the
minimum unit cost of $27.74/m (Figure 3). Therefore, total road
cost was reduced about 25% by the optimization model. Total
amount of sediment delivered to streams from the road section
was estimated as 0.84 ton/km.
The results indicated that total construction cost was the largest
cost component, followed by maintenance and transportation
costs (Table 3). Within the construction cost components,
surfacing cost was the largest, followed by earthwork allocation
cost. Total cost of maintaining culverts and ditches and cleari ne
bushes was the largest cost component in the maintenance costs.
During the search process, the model calculated 147 feasible
solutions out of 1200 automatically generated vertical alignment
alternatives. The solution process took about 15 minutes. The
most of the computation time was spent on calculating
earthwork allocation using LP for each vertical alignment
alternative. The time spent on earthwork allocation increases as
the number intersection points along the roadway increase.
Table 3. Total cost summary table
Cost Components Costs ($)
Total Construction Cost
Road Specifications Values Earthwork Cost — 2109.09
Construction Staking Cost 177.29
Road width 4m Clearing Grabbing Cost 737.05
Cut slopes 1:1 Drainage Cost 406.85
Fill slopes 1.5:1 Seeding Mulching Cost 369.99
Minimum curve radius 18 m Surfacing Cost 3221.65
Minimum length of a vertical curve 15m Water Supply Watering Cost 859.87
Minimum differences between grades 3% Riprap Cost 483.91
Minimum road grade 2% Total Maintenance Cost
Maximum road grade 16 % Rock Replacement Cost 319.45
Minimum distance from road to streams 10 m Grading Cost 84.16
Maximum cut and fill height at centerline 2m Culvert, Ditch, Brushing Costs 1060.62
Design speed 55 km/hr Total Transportation Cost 1166.16
1093