outsourcing
| in place to
>gion. This
-ordinator in
'€ this paper
d to have a
ase gave the
ased on the
act number),
1 the job was
n, with most
h as Local
ance section
'erall 'score'
?,
ews', with a
and project,
:
bo
f allocating
ob;
ors and their
ject staff to
re managing,
monitor the
Director and
th individual
:e, simply by
payroll and
the invoicing
les
-oStation and
available for
grams made
presentation
le. processes.
wer versions
s as custom
etation, title
such as
MicroStation
libraries that
ract.
9, THE IMPACT OF OUTSOURCING ON VICROADS
AND THE PRIVATE SECTOR
9.1 The impact on VicRoads
The outsourcing of say 40-50 % of production or the supply
component of the LIS Department’s work meant a displacement
of 11-14 staff, amounting to a reduction of 25% of staff
numbers at the time of the review leaving sufficient staff to
maintain in-house expertise to manage the work and ensure
VicRoads program and statutory requirements were met. This
reduction in numbers was achieved by natural attrition, re-
deployment or by offering voluntary redundancy packages
(VDP).
Naturally that sort of reduction (25%) caused considerable
uncertainty on the part of staff in the Department and the
regions and projects.
Outsourcing would have to lead to a change in work processes
from conducting surveys to managing the production of
surveys. In the case of photogrammetry, this wasn’t such a big
change, as the section had for some time been contracting out
some or all of its work to a level where the final MicroStation
design file and InRoads terrain modelling could be completed
by VicRoads photogrammetry staff. In fact VicRoads has
always contracted out the aerotriangulation component of jobs,
as it didn’t have any equipment or expertise in that particular
area.
Department staff were required to maintain their commitment
to a quality system, and at the same time ensure the contractors
also worked to quality assurance principles. (Wood 1995)
9.2 The impact on the private sector
As many of the private firms had not done any work for
VicRoads, it meant a very steep learning curve for these firms.
It required a commitment from them to present survey and
photogrammetric data to the standards that VicRoads had set up
for its planning,design and construction requirements. This
meant considerable investment in hardware and software
(MicroStation and InRoads) in order to satisfy these
requirements.
The small size of some firms, one group of firms formed a
consortium to provide the complete range of services required,
and therefore to be able to submit a competitive tender for a
contract.
10. CONTRACT PERFORMANCE
10.1 General performance
Extensive consultation took place with each of the firms
involved in the contract and with all the regional and project
staff involved in administering the contract. Naturally most
firms wanted to see the contract extended for a further period
of twelve months, especially because of the cost involved in
setting up to operate under the contract. This consultation took
place during the term of the contracts and at the end of the first
year.
Overall, the response from firms was mixed. Firms which had
calculated a low percentage of guide for fees tended to have
more problems in reconciling the amount of work involved in
each job and quoting for that job. Some of the smaller firms,
and this included both of the photogrammetry firms, said they
had some difficulties in keeping up with the rate of change of
technology, and the impact that had on the format of the data
required by VicRoads.
Most of the firms readily accepted VicRoads conducting audits
of their firms and their procedures. In fact some firms were
well under way to achieving third party certification for their
Quality systems and a number had already achieved this
certification.
Some minor problems were encountered when the firms were
sub-contracting out work, such as aerial photography or Global
Positioning System (GPS) work. These problems related to the
amount added on as a management portion when quoting for
jobs.
Compared with the surveying contracts, management of the
photogrammetry contracts presented fewer problems. This was
mainly due to a more realistic tender price and the fact that
these firms had been undertaking work for VicRoads as
consultants for a number of years.
The benchmark figure was calculated for each firm based on
information provided during the tender process, and was used
to monitor subsequent quotes for each contract assignment.
The amount of work being contracted out was in the order of
80% for photogrammetry and 4976 for survey services. This
work was fully contract managed by LIS staff. This amounted
to a total of less than $1,000,000 of contracted work.
At the end of the first year, most of the survey contractors
were able to deliver the products and services needed by
VicRoads. However, there was a very steep learning curve for
most firms. Initially all firms were slow or had difficulties in
meeting some of the contractual requirements, such as
insurance, quality plans, and Occupational Health and Safety.
10.2 Performance indicators
By using a representative sample of completed jobs done by all
firms under the contracts, the following performance indicators
were derived. This information was retrieved from the Lotus
Notes database.
Timeliness 81.1% 18.9%
on time late
Re-work 59.5% 35.1% 5.4%
needed low high none
Quality of 91.9% 8.1% 0%
service very good satisfactory deficient
Quality of 81.1% 16.2% 2.7%
final product very good satisfactory deficient
Level of 78.4% 21.6% 0%
supervision low medium high
International Archives of Photogrammetry and Remote Sensing. Vol. XXXI, Part B6. Vienna 1996