-42-
members and is approximately 190 m in length. A stringer is a
horizontal member that transfers load to vertical members—see
Figure 5. Each stringer was approximately 6 m long with a
diameter of 500 mm. The structure has been reinforced with
steel beams in several locations where wooden members have
rotted or been destroyed by termites. A pre-stressed concrete
bridge now takes the traffic load over the Avon River and, at the
time of writing (May 2002), dismantling of the wooden bridge
was well underway.
Prior to disassembly, the wooden bridge was subjected to static
load testing on two of its spans in order to determine its strength
and load sharing properties. Though this bridge was
decommissioned, some 3000 bridges of similar construction
exist within the state of Western Australia. Insight into their
properties was sought through testing in order to determine how
to best maintain such structures.
4.2 Static Load Testing
Static load testing was performed by parking a truck loaded
with concrete and steel weights at various locations on the
bridge. Linear-variable-differential transformers (LVDTs),
digital photogrammetry and TLS were used to measure
deflections and load cells installed to measure force. Data from
these sensors would be used to infer the bridge’s mechanical
properties.
Five different loads were applied during testing, with the
maximum being 65.75 t. These were placed at various locations
(e.g., at mid-span, over columns, etc.). Testing was conducted
on two separate days. On day one, a single 6 m-long section
was tested with some 95 different load conditions. The time
constraints imposed by so many tests dictated that the window
in which photogrammetric and laser scanning measurements
could be acquired was only 2 minutes.
4.3 Photogrammetric Measurement
An Olympus E20 digital camera (array size: 2572 (H) x 1920
(V) pixels) was used to capture a convergent network of 6
images of the targeted span. Though more would have been
desirable, the number of images that could be captured was
limited by the time taken to write image data to the camera’s
memory card. The bridge was imaged prior to the application
of each mass to obtain a no-load epoch for deformation
analysis. Twenty Gb of imagery was captured on the first day
of testing.
More than 200 retro-reflective targets were rigidly fixed to
members of the first span. These consisted of a 25 mm circle of
retro-reflective film centred on a 50 x 50 mm piece of
aluminium angle iron painted flat black. The camera’s flash
5700
Span 3 Stringer Deflections, Load 4 (60.65 tonnes) Centre
1
1
I
I
1
1
E 5600
. Î
5 mm ]
3-1
E
^ 5500
5400
5700
l
r r
1
r
1
r r
1
r
i
Î
1
r T
1
r r
r
3500
4000
4500
5000
5500
6000
6500
7000
7500
£ 5600
- r r
i
r
i
r
Maximum Z deflection:
-8.06 mm
•
3-2
E
^ 5500
5400
5700
I
i
[
i
I
l
Î
1
!
1
t
T
!
3500
4000
4500
5000
5500
6000
6500
7000
7500
1
i
'E 5600
■ r r
l
r
•
3-3
N 5500
5400
5700
r
1
!
I
1
I
1
!
I
\
3500
4000
4500
5000
5500
6000
6500
7000
7500
1
i
1
1
I
? 5600
•
3-4
N 5500
5400
r
1
r
1
r
i
r
r
1
r
1
T
r
T
T
3500
4000
4500
5000
5500
6000
6500
7000
7500
X (mm)
Figure 6. Photogrammetricallv-Determined Deformations.