of the electro-
ld this model
iplete, leading
ns guessed in
electro-valves
lans. A model
ith Pyramide.
present in the
ley needed to
> obstacles for
p and front
sumptions for
model because
ent. This was
nder and filters
Figure 10. Retention tank
These objects stand apart from each other in the cell. No
viewpoint could be found to reliably connect them to nearer
elements. The images captured on the filters and the waste tanks
were as well quite dark. Pyramide showed however that the
dimensions of the retention tank in the initial model needed to
be corrected. The proportions used in this model were wrong.
8
Figure 11. Waste tank, heat exchanger, filters
7.5 Cell walls and floor
Cell walls were assumed to be orthogonal. We supposed as well
that the elements in the cells (tanks, pipes, etc.) were following
the main direction of the room.
Pyramide showed that the floor had two levels. This level
variation of the floor is not obvious to see straight from
monocular images. However, Pyramide indicated that modelling
could not be coherent if we did not make this assumption.
Figure 12. Low walls separating tanks
For retention walls we had to use hypothesis on the dimensions
to place them in the cell. The model of these objects is however
not very reliable since the viewpoints are not adequate.
7.6 Modelling accuracy
The tank inspection task to be realised requires a few centimetre
tolerance on the model accuracy. A theoretical estimation based
on trigonometric calculations taking into account the modelling
methods integrated into Pyramide showed that this requirement
is largely fulfilled. Of course, this cannot be confirmed by on-
site measurements. However, a second hole exists in the ceiling
of the waste room. This hole is obstructed by safety equipment.
This second hole was used to check our estimation of the model
accuracy. It was modelled with Pyramide from images in the
room. The distance found between the two holes in the model
built was 1352 mm. The distance measured in the control room
over the waste room is 1350 mm.
Figure 13. Second hole with fire hose nozzle
7.7 Conclusion on the modelling process
The final model was realised from 90 images captured during
three acquisition campaigns. The global time spent for
modelling is about 5 days. This is longer than what was
expected. The main reasons are the multiple modifications of
the modelling strategy. Especially, it took quite a long time to
prove the unexpected contact between the carrier and the
environment and afterwards to select valid viewpoints.
Although the modelling was less interactive than we expected,
no additional software was developed, and only the existing
functions of Pyramide were used to build the model.
Figure 14. Model of the room
—179—