product; rather they are considered a temporary work material,
because in the implemented digital terrain model, instead of the
Libyan Mean Sea Level altitude datum, they used the EGM96
geod related altitude data. This is according to the (NCB)
estimation results in 40-60 cm mean error, which they plan to
compensate for in the final ortho photograph products. The map
was prepared on the 7% zone of the Libyan Transverse Mercator
Projection, which was tied to the LGD2006 datum. With this
solution, using GPS-based measurements becomes possible
without limits, taking into consideration that conversion
between the WGS-84 and the LGD2006 datums can be easily
solved. Coefficients needed to carry out the 3-parameters datum
transformation are provided by the Surveying Department of
Libya. In doing so, harmonization among development projects
going on simultaneously in the city becomes possible. Further
convenience service is reached in which GeoTiff format
becomes available by cropping the ortho photographs along the
edges of the Transverse Mercator projection mosaics. The
mapping materials provided by the NCB were masked in many
places for security reasons. Taking into consideration that the
Metro network criss-crosses the inner city and intersects with
some areas missing coverage in the NCB's aerial photographs,
we had to substitute the missing parts with cuts from the
satellite imagery, then apply elastic sheet transformation on
these image cuts, and then they were co registered on aerial
photographs. A further significant problem experienced is that
the ortho photograph maps do not provide elevation data for the
Metro network planning process. As a solution, we used
elevation data from the above mentioned hard copy map
scanned as a raster data. During transformation we took into
consideration the effects of the differences of the datums of the
photographs, and then the contours and the photograph of the
discrete altitude points were put in vector forms. This
practically means that plans prepared during the revision of the
plan study of Tripoli Metro are relative to base surface
determined by medium elevation of the Mediterranean Sea.
Overall, it can be said that the produced final map served well
the accuracy requirements of + Im in both latitude and altitude
levels (horizontal and vertical directions) of the revision study
of planning the Metro network. However, it should be noted
that this product is not suitable for further detailed execution
phases and tasks, for example it is not suitable for an execution
plan. Execution plan, especially in densely built-up urban
environments, data accuracy in the range of centimeter is
needed. In essence such accuracy can be achieved only by
terrestrial geodetic survey (Engedy, 2008).
4. PLANNING THE METRO LINES
From line designer’s point of view, it is necessary to have a
whole detailed picture of the planning area. In Tripoli Metro
case the choice was to use a detailed base map which was casted
in a well-known and technically sound projection system that
covers the whole planning area. The projection choice of a base
map that was not prepared by classical terrestrial geodesy
happened for three main reasons: First, the planning area was so
large that surveying it by terrestrial means was not an option.
Second, at the beginning of the planning process, there was no
final decision about the exact line alignments, and consensus
were undergoing among different Libyan authorities about the
exact alignment locations, this fact excluded the possibility for
the designers to consider only narrow stripes of land for the
purpose of lines alignments. Third, the time frame allocated for
the revision study excluded the possibility of following lengthy
terrestrial surveying works.
International Archives of the Photogrammetry, Remote Sensing and Spatial Information Sciences, Volume XXXIX-B7, 2012
XXII ISPRS Congress, 25 August — 01 September 2012, Melbourne, Australia
The availability of satellite imagery and aerial photographs
during different stages of the planning process has made it
possible to flexibly change line alignments according to the
continuous negotiations and agreements between the
contracting Libyan (RPEMB) and other Libyan authorities.
Figure 6, shows deep alignment line that is led away from a
planned traffic node. Figure 7, shows subsurface alignment line
planned not affecting buildings and leaving half the street open
during construction. Figure 8, shows that during construction
only half of the highway needs to be closed. Figure 9, shows
Metro line aligned avoiding a traffic node. And figure 10,
shows Metro line aligned avoiding a bridge foundations.
Figure 6. Deep alignment line led away from a planned traffic
node
Figure 7. Subsurface alignment line not affecting buildings