Full text: Papers for the international symposium Commission VI

114 
In Diagram 2 shown in a graphic manner - -the % of efective 
period of separate stages in 24-month cycle as well as the % 
of labor consumption of seperate stages - in work/days of tech. 
The shown amounts of engaged engineering personnel correspond 
to the acquired output# 
In the realization of the production cycle for 1 day of efective 
work of a technical worker - 2,69ha of finished map in a scale 
of 1:2000 is produced# 
Dividing workers according to office and field workers, and 
technical and engineering workers doing autogrammetrie pbottinq 
untii the last stage of map production in one work day the 
following amount of effective work is completed- 
- autogramme trie al plotted - 34,67 ha 
- remaining work - 3,29 ha 
Diagram 5 shows the % of costs of individual stages of pro 
duction in the cost of the whole objective# 
Description of the above technology of basic map plotting is 
classic technology leading to a map on a graphic basis# 
In Poland u also employed a technology used in the production 
of graphic maps by means of numerical maps /e.g.OPGK Katowice/# 
According to the results of the conducted economic analysis the 
cost of production of 1 ha of the basic map using the numerical 
method is higher than by the use of the classical method: 
by about 22% for map scale 1:2000 
48% for map scale 1:1000 
43% for niap scale 1:500 
Likewise labor consumption of the numerical method with regard 
to impossibility of automatization of many factors in comparison 
with classical method is higher by the following amouts: 
7% for map scale 1:2000 
48% for map scale 1:1000 , 
43% for map scale 1:500# 
4. CONCLUSION * 
It is not possible to organize the optimum production 
cycle from the point of view of its efficiency as well as of 
full use of equipment and manpower because of limited Uigm 
period and production capability of equipment* 
In discribed technology of large scale mapping the cost 
of photograrametrical works / aerotriangulation, plotting / 
is only 8.9%. Most costly /81.3%/ are field works comprise 
interpretation of photos, determination of the property boun 
daries and supplementary surveying. 
The numerical method of map production i3 in Polish con 
dition more costly and more laboriousness then presented above 
technology.
	        
Waiting...

Note to user

Dear user,

In response to current developments in the web technology used by the Goobi viewer, the software no longer supports your browser.

Please use one of the following browsers to display this page correctly.

Thank you.