In Diagram 2 shown in a graphic manner - -the % of efective
period of separate stages in 24-month cycle as well as the %
of labor consumption of seperate stages - in work/days of tech.
The shown amounts of engaged engineering personnel correspond
to the acquired output#
In the realization of the production cycle for 1 day of efective
work of a technical worker - 2,69ha of finished map in a scale
of 1:2000 is produced#
Dividing workers according to office and field workers, and
technical and engineering workers doing autogrammetrie pbottinq
untii the last stage of map production in one work day the
following amount of effective work is completed-
- autogramme trie al plotted - 34,67 ha
- remaining work - 3,29 ha
Diagram 5 shows the % of costs of individual stages of pro
duction in the cost of the whole objective#
Description of the above technology of basic map plotting is
classic technology leading to a map on a graphic basis#
In Poland u also employed a technology used in the production
of graphic maps by means of numerical maps /e.g.OPGK Katowice/#
According to the results of the conducted economic analysis the
cost of production of 1 ha of the basic map using the numerical
method is higher than by the use of the classical method:
by about 22% for map scale 1:2000
48% for map scale 1:1000
43% for niap scale 1:500
Likewise labor consumption of the numerical method with regard
to impossibility of automatization of many factors in comparison
with classical method is higher by the following amouts:
7% for map scale 1:2000
48% for map scale 1:1000 ,
43% for map scale 1:500#
4. CONCLUSION *
It is not possible to organize the optimum production
cycle from the point of view of its efficiency as well as of
full use of equipment and manpower because of limited Uigm
period and production capability of equipment*
In discribed technology of large scale mapping the cost
of photograrametrical works / aerotriangulation, plotting /
is only 8.9%. Most costly /81.3%/ are field works comprise
interpretation of photos, determination of the property boun
daries and supplementary surveying.
The numerical method of map production i3 in Polish con
dition more costly and more laboriousness then presented above
technology.